GRi in Parliament 24 – 10 - 2002

 

 

Parliament concerned about rural electrification project

 

Accra (Greater Accra) 24 October 2002 - Members of Parliament on Wednesday expressed concern about delays in the execution of on-going rural electrification programmes under the Phase-Three of the Self-Help Electrification Project.

 

The members' questions centred on whether the project was on schedule, what has slowed down its pace, whether, because of lack of funds and what the time schedule of the SHEP-Three.

 

Godfred Otchere, NPP MP for Ayesuano had asked the Minister for Energy why Kofi Pare, near Kraboa Coaltar has not been connected to the National Grid despite the fact that it has met the requirements set out under SHEP-Three.

 

Kobina Tahir Hammond, Deputy Minister for Energy on behalf of the Minister said following the completion of the High Voltage and Low Voltage networks, materials for the service connections for Kofi Pare were initially released to the Regional offices of Electricity Company of Ghana in the Eastern Region.

 

He said however, due to some administrative hiccups at the regional offices, works on these connections have now started and would be completed by the end of next month. John Mahama, NDC-Bole asked the Deputy Minister what had slowed down the pace of the SHEP project and the Minister said he needed notice to give an informed answer.

 

After a series of debates and arguments from the Majority and Minority concerning the SHEP-Three project, Kenneth Dzirasah, the Second Deputy Speaker, who was in the chair asked the Deputy Minister whether the project was on schedule to which he answered in the affirmative.

 

Joe Gidisu, NDC- North Tongu asked about the time schedule on the terms of the SHEP- Three projects and the Deputy Minister said it was to stop by the end of this year. He explained that some communities, especially in the Northern sector have been unable to purchase low tension poles for their electrification projects, which has delayed most of the projects.

 

Gidisu drew the attention of the Deputy Minister to some communities in the Northern parts of the Volta Region, which have purchased the poles but have still not been connected and the Minister said such communities would be assisted to get connected to the National Grid.

 

Otchere, in another question asked why the on-going electrification project at Asuboi on the Nsawam-Suhum road has been suspended by the contractor. Hammond said the project has not been suspended since concrete poles were originally released for the construction of the High Voltage networks.

 

He said, however, due to the hilly terrain of some portions of the line route, the consultants recommended that wooden poles should be used to replace the concrete poles in the hilly areas. Hammond said the replacement poles have been ordered and it was expected to be delivered to the site by November to enable the completion of the project by the end of December, 2002.

 

Otchere asked whether the Minister was aware that the contractor had not been on site for the past one year and the Minister said it might be because of change of poles that caused the delay of the project.

 

Seidu Adamu, NDC-Bibiani/Anhwiase/Bekwai asked whether beneficiary communities are under any compulsion to offer communal labour in the erection of the poles and the Minister said it was not a requirement.

GRi…/

 

Send your comments to viewpoint@ghanareview.com